feature
“Tricks” of the Trade
Think Unethical Glaziers Can’t Outsmart
Architects? Think Again
by Penny Stacey
Shortcuts—they happen in every industry and trade. The disreputable
try to save a buck and skip a step, or substitute a product, betting that
no one finds out—not even you, the architect.
“I think in today’s economy probably 50 to 70 percent of
what I see has been short-cutted—or maybe a better word is short-changed,”
says one contract glazier who preferred not to be identified in part due
to the sensitive nature of the issue. “It just kind of comes with the
competitive nature of the world today. Everybody’s looking for a competitive
edge. How do they get a few more dollars out of the job to make them get
more out of the job or put themselves in a position to be the low bidder?”
Sometimes, whether or not shortcuts are taken depends on
how the job was obtained and the quality of the glazing contractor that
won the job, according to a team of experts with whom Architects’ Guide
to Glass and Metal consulted for this article. “The negotiated job typically
doesn’t see as many shortcuts or deletions as the hard-bid job will,”
says one. “That’s not to say that the glazing contractor who has negotiated
a job won’t end up taking shortcuts—but it’s probably not as common.”
The Shortcuts
Though industry experts say shortcuts can occur in a myriad of ways, following
are a few of the most common and egregious ones:
• A non-specified product is substituted for a spec-ed one. You
spent time with manufacturers’ reps, you reviewed technical data sheets
and you selected products that you thought to be the best fit for the
job. Still, a different glass product was used—and you don’t even know
it. Sometimes this might lead to a code violation, but often not.
• Undersized glass. Even though you selected a certain-weighted
glass it may not be what you get. This shortcut is quite common, according
to our experts. In some cases a thinner glass product is used than what
is called for. “It’s common because it’s hard to catch,” says one of our
team members.
• Misapplication of materials. You designed an impressive storefront
to feature long spans of curtainwall; but in the end it didn’t make the
job. An example of this might be using storefront materials in applications
where bigger sections of curtainwall should have been used, because it’s
cheaper and easier to fabricate. Even though a system failure can result,
this happens more frequently than you might expect, according to experts.
• Material substitution. The specification you wrote called for
a sealant to meet a given set of performance requirements. In the end,
though, someone chose to go with something else. It happens—whether you
know it or not. This can include caulking, sealants, specified baker rods,
undersized fasteners, or even not using enough or proper fasteners, according
to experts.
• Unreinforced mullions. And even after you’ve drawn the project
in a manner to be structurally sound, sometimes even those critical enforcement
steps can be skipped. One expert recalled a situation in which he inspected
a building that was only about 10 years old and having a repeated problem
with broken glass. “There was a piece of steel that was supposed to be
running through the vertical mullions,” recalls the expert. “I was able
to pry it open and there was no steel in there. I started doing some calculations
with the engineer and found that the glass that had been installed less
than 10 years prior was not to code and nor were the frames.”
This particular shortcut led to major repercussions. Since
the aluminum mullions hadn’t been reinforced, they blew in and broke all
this glass. “For sure the steel mullions would not have deflected and
caused this unbelievable amount of breakage,” he said.
The Bottom Line
Despite possible repercussions, why do these things occur? One is a feeling
among some glaziers that today’s codes are excessive and such shortcuts
only right a wrong. Experts suggest that some glazing contractors might
think, “We’ve never done it that way before and we’ve never had a problem,”
leading them to take a shortcut. As with so many other situations, communication
and solid supplier relationships can help. As architect Chris Rose with
Chris Rose Architects in Johns Island, S.C., says, “Knowing and having
a relationship with your supplier is key in assuring a certain specified
product is installed properly.”
Penny Stacey is a contributing editor for Architects’
Guide to Glass and Metal magazine and editor of USGlass magazine. She
can be reached at pstacey@glass.com. Read her blog at http://penny.usglassmag.com,
follow her on Twitter @USGlass, and like USGlass Magazine on Facebook
to receive the latest updates.
Architects' Guide to Glass & Metal
© 2012 Copyright Key Communications Inc. All rights reserved.
No reproduction of any type without expressed written permission.
|